Upcoming meetings and activities are listed below: - Saturday, September 11 9 am - FINAL WORKDAY for the Bishop house. A milestone! Food provided
by the Bishop Family!
- Monday, October 4, 4 pm - Dedication of Bishop Home, plus
recognition of Ohio's 3000th Habitat Home.

Celebrating 3000 Habitat homes built in Ohio (and the 1st home built by Putnam County Habitat! -
-
- Thursday, October 7 - Open Board Meeting, 7 pm, Ottawa Presbyterian Church
- 2011 - Construction of House #2 will begin in Leipsic
Build #1 Schedule - located at 641
South Oak Street in Ottawa This is an ideal
schedule, planned for 16 weekends. Dates will change due to weather or material, contractor and volunteer availability.
Please be flexible! Items that are finished are shown in this color.Pre-volunteer
weeks 1-3+ (April 19-May 15) Excavate driveway and install base stone Dig, form and pour footers
Excavate crawlspace and garage, backfill with stone
Form and pour crawlspace and garage floors (all completed)Week
4 - May 22--First Day for General Volunteers Install "I" joist and OSB sub-floor (finished May 22) May 26-Extra workday with double shifts (8 am to 4 pm &
4 pm to 8 pm)
Frame and set exterior walls (house and garage) (Interior walls finished
also)NOTE: No crews were scheduled for Memorial Day Weekend
(May 29) Week 5 - June 5 Frame and set exterior walls (house and garage)
(finished May 26)
Apply exterior sheeting, level and brace walls (finished June 2 &
3)Week 6 - June 12 Set roof trusses (finished June 3) Sheet and shingle roof (roof sheeting finished
June 5, singles in process as of June 7)
Caulk! Caulk! Caulk! (Stage 1 caulking is done on June 12...more later) Build front deck with steps and railings (August 11-13)Week
7 - June 19
Sheet and shingle roof (finished June 11) Install exterior blue board and
house wrap (finished June 19) Install windows (moved to July 6 with Sheriff Beutler and sheriff's office crew) Exterior doors (done!) and garage door (done!) Build and set interior walls (finished May 26)Week 8 - (Week ending June 26) Complete electrical rough-in (in process as of June
16) Insulate interior
(finished June 26) Begin siding installation below windows (started June 26) Begin soffit installation (started
June 26, finished July 21) Volunteers - pour driveway, sidewalks, and rear patio (August 11-13)No work was scheduled for July 3 (Holiday Weekend)Week
9 - (Week ending July 10)
Professional contractor only on weekdays Rough-in plumbing, set shower and tub Install
HVAC (Duct work in process as of June 8) July 7 - Install
windows (thanks to Sheriff Beutler and his volunteers) Volunteers - Inspection #1....caulk, caulk, caulk! Finish
driveway, sidewalks, and rear patio (August 11-13)Week 10 - July 17 Insulate walls (exterior) finished June 19. Install ceiling drywall
(started July 17) Finish siding installation
(finished July 24)Week 11 - July 24 Finish ceiling drywall installation (finished July 28) Begin drywall installation on vertical walls Week 12 - July 31 August 11-16
(Professional contractor - finish drywall)Week 13 - August 14 No general volunteers scheduled - enjoy the day! Week 14 - Week
of August 21 Prime
& paint ceilings and walls (done)
Insulate ceiling (done!) Install
cabinets in kitchen and bathrooms
Install counter tops
Finish electrical (outlets, switches, and lighting-done)Week 15+ - Week of August
28, following weekdays
Finish plumbing (waiting for toilet shipment)
Install interior doors with hardware (done)
Install finish trim (done)No crews will be scheduled on Labor Day weekend.Week
16 - September 11 Cleaning, installation
of medicine cabinets, closet shelving & rods, power wash siding, etc.
Installation of carpeting and landscaping (to be done at very end)
Inspection #2 Punch OutTURN OVER KEYS TO BOARD, THEN HOMEOWNER A dedication will take place October 4 at 4 pm in conjunction
with World Habitat for Humanity Day as established by the United Nations. Also, floor coverings may be
installed after the dedication has taken place.
|
 |
|
|
|
|
|
 |